Project Update 10/15/2015

A&M has the lane closure from the Middleburg Bank to S. Madison Street. This required the signal put into flash, which you will need to turn back on around 3:30pm. My field guy Jovi will call you if we finish early or end up going later than that as we get closer to cutoff time.

After Completion of our work today, you can remove remaining bagged meters between Middleburg Bank and S. Pendleton Street on EB Route 50.

Friday 10/16/2015:

Please Bag the Meters from S. Madison Street to S. Liberty Street on EB Route 50.

A&M will have a closure from Just before S. Madison Street to the East Side of S. Liberty Street. It will be a continuation of what we complete today. We will need the Signal put on Flash Again at 9am and turn back on around 3:30 pm.

You Can Remove All bags in the afternoon from S. Madison Street to S. Liberty Street on EB Route 50.

Monday 10/18/2015:

Please bag the meters from the Plains Road to the US Post Office Entrance. We need the meters bagged on both Sides of the Road. We will have a closure from West of the Plains Road to Just West of S. Pendleton St. We will pre-excavate a hole at the BB&T Bank and place a steel plate overnight. The plate will be removed and road restored on Tuesday.

NOTE: Significant impact on BB&T drive thru

Please leave bags in place overnight.

Tuesday 10/18/2015

Complete work in front of BB&T Bank. We will have a closure from West of the Plains Road to Just West of S. Pendleton St.

leave bags in Place Overnight.

Wednesday 10/19/2015

Please place additional bags from the US Post Office to S. Pendleton Street both Sides. We will have Lane Closures from S. Pendleton Street to the WB Side of the Plains Road.

These are subject to change based on weather, production ect. I will provide more information as we formulate and monitor progress.

As always thank you for your continued support during this project.

All information provided by: Brian Grover A&M Concrete Corporation

First Stage of the route 50 project starts

Thursday, October 15

Meters on both sides of the street will be bagged “No Parking” between The Plains Road and Pendleton Street. The bags will be removed on Friday, October 16 at the conclusion of work. Parking will be available for both sides of the street over the weekend.

Monday, October 19

Meters on both sides of the street will be bagged “No Parking” between The Plains Road and Pendleton Street. The Bags will be removed at the conclusion of work on Thursday afternoon October 22.

The updates will be posted here as they come about.